The first of two new nuclear reactors being built at Plant Vogtle has gone into commercial operation, Georgia Power officials announced Monday.
Unit 3 at the plant south of Augusta went into service early Monday morning, seven years after originally scheduled and at more than double the original cost estimate.
The new unit is the first newly constructed nuclear reactor in the U.S. in more than 30 years and can power an estimated 500,000 homes and businesses.
“The Plant Vogtle 3 & 4 nuclear expansion is another incredible example of how Georgia Power is building a reliable and resilient energy future for our state,” said Kim Greene, the Atlantabased utility’s chairman, president and CEO.
“Today’s achievement … marks the first day of the next 60 to 80 years that Vogtle Unit 3 will serve our customers with clean, reliable energy.”
Chris Womack, president and CEO of Georgia Power parent Southern Co., called Monday a “historic day” for the company, for Georgia, and for the energy industry.
The second new reactor, Unit 4, is projected to go into commercial operation late this year or early in 2024. Last week, the Nuclear Regulatory Commission gave its final go-ahead for Unit 4, issuing a finding that the new reactor will be operated in conformance with federal regulations.
In light of the delays and cost overruns, the project’s critics for years have been calling on Georgia Power to abandon nuclear power and pursue other options including renewable energy. Last week, a panel of experts told members of the Georgia Public Service Commission (PSC) during a hearing that Georgia Power’s 2.7 million customers will pay significantly more for the nuclear expansion than if the company had used natural gas.