Tri-CoGo celebrates 500 miles of fiber construction

The Tri-CoGo Team, fiber consultant Conexon, and contractor Ervin Cable Construction celebrated reaching 500 miles of installed fiber on Tuesday, May 17, at the Tri-County EMC office in Gray. According to Project Manager Alan Boggs, since May of 2021, crews have hung 2,344,320 feet of strand, buried 269,280 feet of underground duct, and attached 2,678,000 feet of fiber across Jones, Wilkinson, ...

To access content, please login or purchase a subscription starting at just $5.